Beaver, PA
15009
United States of America
Latitude: 40.6960437
Longitude: -80.3047846
http://www.netl.doe.gov/coal/refshelf/ncp.pdf - canceled but no date given.
AES proposes to install a new 2,155MMBTU/HR CFB boiler and at the same time retire four existing pulverized coal boilers. This new configuration will generate approximate 180 MW, compared to the current 125 MW. : Permitting staff reviewed the emissions data to see whether the modification would trigger major NSR requirements. Assuming past emissions were compliant, the modification would not trigger major NSR for any pollutant.Â