[NukeNet] Browns Ferry repair costs $90 million above budget [$1.8 billion project]

Wild Clearing wildclearing at wildclearing.com
Tue Dec 18 05:55:03 EST 2007



Browns Ferry repair costs $90 million above budget --  [$1.8 billion  
project]

By Dave Flessner, Staff Writer
The Chattanooga Times Free Press

Chattanooga, TN - The repair and upgrade of TVA's oldest nuclear  
reactor ended up costing $90 million more than originally budgeted,  
and so far the unit has operated at less than its forecasted long- 
term reliability, according to TVA documents filed with the U.S.  
Securities and Exchange Commission last week.

But TVA's chief operating officer said Monday that the restart this  
spring of the Unit 1 reactor at the Browns Ferry Nuclear Power Plant  
in Alabama is saving TVA money and will be a better-than-expected  
investment because of the rising costs of other energy sources.


"Even at the higher costs, Browns Ferry still represents a  
significant value for TVA," said TVA Executive Vice President Bill  
McCollum Jr. "The payback should actually be better than the original  
estimates, primarily because the value of that energy is greater today."

In its first four months of operation, the Browns Ferry unit saved  
TVA $196 million compared with more expensive power the utility  
otherwise would have had to buy to meet its power demand, Mr.  
McCollum said.

In its annual financial report, TVA said it finished the Browns Ferry  
project on time and within 5 percent of its original budget forecast.  
That compares favorably to TVA's nuclear power construction program a  
generation ago when some reactors cost several times more than  
originally forecast.

The first reactor at the Watts Bar Nuclear Plant near Spring City,  
Tenn., for instance, took 22 years to build and cost more than $6.8  
billion, or nearly 10 times its original estimate.

Critics of nuclear power contend that the cost overruns at Browns  
Ferry raise concerns about the costs of nuclear plants as TVA and  
other utilities make plans to add more reactors. Stephen Smith,  
executive director for the Southern Alliance for Clean Energy in  
Knoxville, said TVA has "really hyped the advantages of nuclear power.

"Browns Ferry certainly came out better than the huge cost overruns  
we saw in the past with these nuclear plants, but $90 million is  
still a significant amount of money," Mr. Smith said. "The plant also  
is running below the optimistic production levels TVA said it would  
achieve and has had a lot of trips that raise questions about whether  
TVA rushed to get it finished."

Since the Unit 1 reactor at Browns Ferry resumed power generation on  
June 2, the plant has operated 78.8 percent of the time. The reactor  
has had five unplanned shutdowns, or more than 10 times the industry  
average for such outages at operating plants, according to data  
compiled by the Nuclear Energy Institute.

But TVA spokesman John Moulton said such shutdowns are more common  
when a new plant is being started or a unit is being reactivated  
after a prolonged outage. TVA shut down the Browns Ferry reactor  
because of safety concerns in 1985 and the unit remained idle until  
this spring.

"These type of outages are to be expected when you restart a unit  
like this," he said. "The capacity factor is comparable to what TVA  
saw with units 2 and 3 after prolonged outages at Browns Ferry and  
those reactors are now performing very well."

Inspectors for the Nuclear Regulatory Commission reviewed the five  
outages at the Unit 1 reactor at Browns Ferry in November. NRC  
spokesman Ken Clark said Monday the NRC expects to issue its findings  
from its review in early 2008.

Mr. McCollum said in November that he did not anticipate any problems.

"I think they (NRC staffers) were well satisfied with the work that  
our staff has done to investigate the causes and see what we need to  
do," he said.

In its financial filings, TVA said the $90 million cost overrun  
primarily was because of the expense of boosting the power output of  
the unit by another 130 megawatts. TVA conducted a detailed  
engineering plan to repair Browns Ferry Unit 1 before the TVA board  
decided in May 2002 to restart the unit.

The initial $1.8 billion, 60-month budget for the Browns Ferry  
repairs included plans to boost the power output of the unit by more  
than 10 percent. But Mr. McCollum said that portion of the project  
required licensing approval and costs more than originally forecast.

The restart of the unit after its 22-year outage won acclaim from  
industry groups and President Bush. During a visit to the plant in  
June, the president called the Browns Ferry reactor "a reliable  
source of low-cost energy."

"This is a demonstration that one is capable of doing a job on time  
and on budget," Mr. Bush told more than 200 plant employees during a  
speech touting the advantages of nuclear power.

In November, the editors of Platts Insight, a global energy news  
service owned by McGraw-Hill Co., recognized the recovery of Browns  
Ferry Unit 1 as their Energy Construction Project of the Year. During  
the judging of projects in London earlier this year, one of the  
Platts' reviewers said the restart of Browns Ferry "was like  
converting a DC-3 airplane to a 747 in midair."

Wes Rehberg
Wild Clearing
www.wildclearing.com
www.nonviolentways.org





-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://mail.energyjustice.net/pipermail/nukenet_energyjustice.net/attachments/20071218/5b727860/attachment.html 


More information about the Nukenet mailing list