[NukeNet] *****SPAM***** Re: [no-new-nukes-yall] Browns Ferry repair costs $90 million above bud

Dolph Honicker djhonicker at msn.com
Tue Dec 18 17:41:41 EST 2007


I looked at what Raymond sent.  The capacity factors were for Vermont Yankee.  Brown's Ferry reactor unit 1 has been down since 1985 until 2007.    Can anyone find information on it?
Jeannine


From: bob at bobstannard.comTo: shadis at prexar.com; djhonicker at msn.com; wildclearing at wildclearing.com; no-new-nukes-yall at yahoogroups.comDate: Tue, 18 Dec 2007 13:47:52 -0500CC: dfreeman at renewablegroup.com; nukenet at energyjustice.net; cevan at sover.net; dfreeman at h2carco.com; harvey at nukebusters.org; deb at nukebusters.org; nucnews at yahoogroups.comSubject: Re: [NukeNet] *****SPAM***** Re: [no-new-nukes-yall] Browns Ferry repair costs $90 million above budget [$1.8 billion project]








Very helpful, Ray.  Thank you.
 
Bob 
 

------------------------------------------------------------
Stannard Associates, Inc.
Robert J. Stannard, Pres
117 Sleepy Hollow Dr.
Manchester Center, Vt. 05255
802-362-3658 phone/fax
802-345-0786 cell
bob at bobstannard.com
 




From: Raymond Shadis [mailto:shadis at prexar.com] Sent: Tuesday, December 18, 2007 12:58 PMTo: Bob Stannard; 'Dolph Honicker'; 'Wild Clearing'; 'Group No-New-Nukes'Cc: 'Freeman, Dave #2'; 'List Nukenet'; Chris Williams; 'Freeman, S. David'; Harvey Schaktman; Deb Katz; nucnews at yahoogroups.comSubject: *****SPAM***** Re: [NukeNet] [no-new-nukes-yall] Browns Ferry repair costs $90 million above budget [$1.8 billion project]
 
Dear Bob,  Life time capacity factors might be had from a search of the NRC website - www.nrc.gov.  Inparticular one might want to look at back issues of NUREG 1350.  The 2002 and 2005 issues yield the following for VY: AVG CAPACITY FACTOR (%)1996 - 84.81997 - 95.51998 - 71.91999 - 90.92000 - 101.52001 - 93.42002 - 88.72003 - 99.5Generally, the approximately biennial cycling in this set of numbers is largely attributable to refueling outages. Where capacity factors fall below those of fossil fuel plants, one might legitimately add in the difference in cost between spot market replacement power and long term alternatives.  "Add the cost of building it,  repairing it,  interest on it's debt, total operating cost, and the cost of the fuel."  These costs are included in the price of VY generated electricity . They are all ready added in - along with, given certain exceptions,  high and low level waste disposal and decommissioning."Calculate the true cost of   the amount of total electricity it has produced, not just the cost of fuel."  Some costs to the public -in the form of tax dollars - are not added in to the cost per kilowatt that consumers pay. Tax- breaks (as in Vermont), subsidies, and R&D and certain other uncompensated costs, for example, health impact costs, some aspects of emergency planning, security, some federal and state oversight costs, and environmental damages are not added in and should be added in the actual cost per KW.  There are likely some other hidden costs that do not fall under these broad categories..(negative impacts on real estate values and tourism?) ...leave it to more discerning minds than mine to identify and quantify them.Thanks for your interest and all the good work that you do. RayConsultant toNew England Coalition At 07:13 AM 12/18/2007, Bob Stannard wrote:
NukeNet Anti-Nuclear Network (nukenet at energyjustice.net)I cannot emphasize enough the importance of Jeannine’s inquiry below.  The article in question from Wes concerned me as it pertains, to some degree, to the case that I am formulating for the closure of the VY plant here in Vermont.  I would welcome a response to Jeannine’s question if one exists. ThanksBob Stannard ------------------------------------------------------------Stannard Associates, Inc.Robert J. Stannard, Pres117 Sleepy Hollow Dr.Manchester Center, Vt. 05255802-362-3658 phone/fax802-345-0786 cellbob at bobstannard.com 



From: nukenet-bounces at energyjustice.net [ mailto:nukenet-bounces at energyjustice.net] On Behalf Of Dolph HonickerSent: Tuesday, December 18, 2007 7:03 AMTo: Wild Clearing; Group No-New-NukesCc: Freeman, Dave #2; List Nukenet; nucnews at yahoogroups.com; Freeman, S. DavidSubject: Re: [NukeNet] [no-new-nukes-yall] Browns Ferry repair costs $90 million above budget [$1.8 billion project] If you include the time from when this reactor was first brought on line, until today, what is the capacity factor, or the availability factor?  Anyone know? Add the cost of building it,  repairing it,  interest on it's debt, total operating cost, and the cost of the fuel.  Calculate the true cost of   the amount of total electricity it has produced, not just the cost of fuel.  How much per kilowatt hour are we paying?  Has anyone ever done this? Jeannine



CC: nukenet at energyjustice.net; nucNews at yahoogroups.comTo: no-new-nukes-yall at yahoogroups.comFrom: wildclearing at wildclearing.comDate: Tue, 18 Dec 2007 05:55:03 -0500Subject: [no-new-nukes-yall] Browns Ferry repair costs $90 million above budget [$1.8 billion project]  Browns Ferry repair costs $90 million above budget --  [$1.8 billion project] By Dave Flessner, Staff WriterThe Chattanooga Times Free Press Chattanooga, TN - The repair and upgrade of TVA's oldest nuclear reactor ended up costing $90 million more than originally budgeted, and so far the unit has operated at less than its forecasted long-term reliability, according to TVA documents filed with the U.S. Securities and Exchange Commission last week. But TVA's chief operating officer said Monday that the restart this spring of the Unit 1 reactor at the Browns Ferry Nuclear Power Plant in Alabama is saving TVA money and will be a better-than-expected investment because of the rising costs of other energy sources.  "Even at the higher costs, Browns Ferry still represents a significant value for TVA," said TVA Executive Vice President Bill McCollum Jr. "The payback should actually be better than the original estimates, primarily because the value of that energy is greater today." In its first four months of operation, the Browns Ferry unit saved TVA $196 million compared with more expensive power the utility otherwise would have had to buy to meet its power demand, Mr. McCollum said. In its annual financial report, TVA said it finished the Browns Ferry project on time and within 5 percent of its original budget forecast. That compares favorably to TVA's nuclear power construction program a generation ago when some reactors cost several times more than originally forecast. The first reactor at the Watts Bar Nuclear Plant near Spring City, Tenn., for instance, took 22 years to build and cost more than $6.8 billion, or nearly 10 times its original estimate. Critics of nuclear power contend that the cost overruns at Browns Ferry raise concerns about the costs of nuclear plants as TVA and other utilities make plans to add more reactors. Stephen Smith, executive director for the Southern Alliance for Clean Energy in Knoxville, said TVA has "really hyped the advantages of nuclear power. "Browns Ferry certainly came out better than the huge cost overruns we saw in the past with these nuclear plants, but $90 million is still a significant amount of money," Mr. Smith said. "The plant also is running below the optimistic production levels TVA said it would achieve and has had a lot of trips that raise questions about whether TVA rushed to get it finished." Since the Unit 1 reactor at Browns Ferry resumed power generation on June 2, the plant has operated 78.8 percent of the time. The reactor has had five unplanned shutdowns, or more than 10 times the industry average for such outages at operating plants, according to data compiled by the Nuclear Energy Institute. But TVA spokesman John Moulton said such shutdowns are more common when a new plant is being started or a unit is being reactivated after a prolonged outage. TVA shut down the Browns Ferry reactor because of safety concerns in 1985 and the unit remained idle until this spring. "These type of outages are to be expected when you restart a unit like this," he said. "The capacity factor is comparable to what TVA saw with units 2 and 3 after prolonged outages at Browns Ferry and those reactors are now performing very well." Inspectors for the Nuclear Regulatory Commission reviewed the five outages at the Unit 1 reactor at Browns Ferry in November. NRC spokesman Ken Clark said Monday the NRC expects to issue its findings from its review in early 2008. Mr. McCollum said in November that he did not anticipate any problems. "I think they (NRC staffers) were well satisfied with the work that our staff has done to investigate the causes and see what we need to do," he said. In its financial filings, TVA said the $90 million cost overrun primarily was because of the expense of boosting the power output of the unit by another 130 megawatts. TVA conducted a detailed engineering plan to repair Browns Ferry Unit 1 before the TVA board decided in May 2002 to restart the unit. The initial $1.8 billion, 60-month budget for the Browns Ferry repairs included plans to boost the power output of the unit by more than 10 percent. But Mr. McCollum said that portion of the project required licensing approval and costs more than originally forecast. The restart of the unit after its 22-year outage won acclaim from industry groups and President Bush. During a visit to the plant in June, the president called the Browns Ferry reactor "a reliable source of low-cost energy." "This is a demonstration that one is capable of doing a job on time and on budget," Mr. Bush told more than 200 plant employees during a speech touting the advantages of nuclear power. In November, the editors of Platts Insight, a global energy news service owned by McGraw-Hill Co., recognized the recovery of Browns Ferry Unit 1 as their Energy Construction Project of the Year. During the judging of projects in London earlier this year, one of the Platts' reviewers said the restart of Browns Ferry "was like converting a DC-3 airplane to a 747 in midair." Wes RehbergWild Clearingwww.wildclearing.comwww.nonviolentways.org      __._,_.___ Messages in this topic (1) Reply (via web post) | Start a new topic Messages | Files | Photos | Links | Database | Polls | Members | Calendar MARKETPLACE
 
Earn your degree in as few as 2 years - Advance your career with an AS, BS, MS degree - College-Finder.net. 
 
Fed Lowers Rates Again - Think you pay you much for your mortgage? No SSN Required - Estimate New Payment. Change settings via the Web (Yahoo! ID required) Change settings via email: Switch delivery to Daily Digest | Switch format to Traditional Visit Your Group | Yahoo! Groups Terms of Use | Unsubscribe Recent Activity 

 1 
New MembersVisit Your Group HDTV SupportThe official SamsungY! Group for HDTVsand devices.Dog Groupson Yahoo! Groupsdiscuss everythingrelated to dogs.Moderator CentralYahoo! GroupsGet the latest newsfrom the team..__,_._,___ _______________________________________________________________________Subscribe/Unsubscribe Here: http://www.energyjustice.net/nukenet/Change your settings or access the archives at:http://mail.energyjustice.net/mailman/listinfo/nukenet_energyjustice.net 
-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://mail.energyjustice.net/pipermail/nukenet_energyjustice.net/attachments/20071218/11400f6c/attachment.html 


More information about the Nukenet mailing list