[NukeNet] Individual Action in progress, Florida Alliance update, Part 2.

Minimushomines at aol.com Minimushomines at aol.com
Mon Jan 7 20:03:57 EST 2008


 
Dear, 
Nuke net, grass roots independent, environomic activist, advocates, (Twigs,  
swarmers and opposers of toadies, chameleons and people that do unmentionable  
things to swine. 
 
Part 2) Pre Hearing  statement.             
 
 Comments and other input appreciated from the above mentioned social  
subgroups.
 
 
..........................................................................................................................................................
 

BEFORE THE PUBLIC SERVICE COMMISSION 


Re: Florida Power and Light Company’s                                  DOCKET 
NO. 070650-EL 
Petition to Determine Need for FPL Turkey  Point 
Nuclear Units 6 and 7 Electrical Power  Plant                           
Dated: January 4, 2008 
INTERVENORS BOB AND JAN KRASOWSKI’S  PREHEARING STATEMENT 
Pursuant to Order No. PSC-07-0869-PCO-EL, issued October 30,  2007, 

Intervenors, Bob and Jan  Krasowski hereby file their Prehearing Statement. 
1.      All known Witnesses. 
None. 
2.      All known exhibits. 
None at this time. Pursuant to Order No.  PSC-07-0869-PCO-EL, issued          
October 30, 2007, #IV and # VII, E, we reserve the right to present  exhibits 
at the Prehearing conference scheduled for January 14, 2008.          
3. Basic Position Statement 
A large variety of efficient resource  management as well as power management 
and generating options are available to  the utilities that service the 
residential, institutional and business energy  demands of Florida.  In assessing 
the options for meeting these energy demands we have come to  the conclusion 
that the nuclear project proposed by FP&L for Turkey Point  does not represent 
the best choice available to service FP&L customers. We  contend that when 
compared to other options and strategies the Turkey Point  6&7 proposal poses an 
extended period of economic risk that is unreasonable  and diminishes the 
economic wellbeing of FPL’s Florida customers now and in the future.  Therefore, we 
request that the petition  for determination of need for Turkey Point 6&7 be  
denied. 
FP&L’s representatives allege that the  Turkey Point 6&7 proposed project 
meets the needs criteria established by  the State of Florida in FS403.519(4) in 
that the project contributes to FPL’s  power system’s  reliability and  
integrity, it’s fuel diversity, base load generation capacity, and its effort to  
deliver adequate electricity at a reasonable cost. That it continues to be a  
viable option after any renewable energy sources and technologies or  
conservation measures that may be taken or are reasonably available to FPL that  might 
mitigate the need for the proposed generating units has been considered,  
while also providing the most cost effective source of  power. 
It is our belief, based on our research, that  the projected cost of this 
proposal as alleged by FP&L does not represent an  accurate assessment of the 
actual costs of the project. That the cost of  managing the waste associated with 
this nuclear project has not been accurately  identified.  Future costs 
attributed  to CO2 and other green house gas (GHG) emissions attributed to the 
mining,  milling, and refining of nuclear fuel have not been adequately accounted 
for.  Potential cost charged for radioactive emissions from mining and 
operations are  not mentioned. The availability and cost of water need to be  
considered. 
It is our contention that every dollar of  FP&L rate payer money (14 to 24 
Billion Dollars) proposed to be spent on the  proposed Turkey Point 6&7 nuclear 
power project could be better spent on  efficiency, conservation and 
renewables; financing programs that may include  embellishing existing or creating new 
DSM programs, leveraging through cost  sharing the expansion of net metering / 
distributive energy programs. The  integration of solar thermal and geo 
thermal applications can mitigate peak  load. The more efficient use of the 
existing base load can eliminate the need  for new base load capacity. We also see a 
slowing of growth in Florida that calls into  question the proponent’s 
projection for need. New building design criteria will  also reduce the need for new 
generation. 
4.                                      Statement of Positions and issues 
ISSUE 1:         Is there a  need for the proposed generating units, taking 
into account the need for  electric system reliability and integrity, as this 
criterion is used in Section  403.519(4), Florida Statutes? 
Position: No, the current and future  needs of Floridian’s power can be met 
with greater reliability and integrity  with the implementation of 
efficiency/conservation measures, the graduated  increased use of renewable technologies, 
a generous net metering / distributive  energy program.     
ISSUE 2:         Is  there a need for the proposed generating units, taking 
into account the need for  fuel diversity, as this criterion is used in Section 
403.519(4), Florida  Statutes? 
Position: No, distributive  generation of thermal and pv solar and gas 
capture for agriculture are preferred  methods of establishing fuel diversity over 
nuclear in the existing energy needs  environment. 
ISSUE 3:        Is  there a need for the proposed generating units, taking 
into account the need for  base-load generating capacity, as this criterion is 
used in Section 403.519(4),  Florida Statutes? 
Position: No, there already exists sufficient base-load. Future  base-load 
and current base-load can incrementally be provided and replaced by  efficiency 
and cleaner new renewable applications. Population decline and  greater 
efficiencies allow current existing base-load capacity to satisfy the  need. 
ISSUE 4:         Is  there a need for the proposed generating units, taking 
into account the need for  adequate electricity at a reasonable cost, as this 
criterion is used in Section  403.519(4), Florida Statutes?   
Position:  No, reasonable cost has not been  established here.  The cost of 
the  waste storage, CO2 and other greenhouse gases related to  fuel  assessment 
are not complete.  Water costs remain a question. We  already have adequate 
electricity.  The economic costs of insuring the risks associated with an 
unforeseen  event may be limited to FPL but extend to the overall population in the 
amount  of billions and billions of dollars and need to be considered in the 
cost/risk  assessment and in relationship to the other options. 
ISSUE 5:         Are there any renewable energy sources and technologies or  
conservation measures taken by or reasonably available to Florida Power &  
Light Company which might mitigate the need for the proposed generating  units? 
Position: Yes, (An assessment  of the meaning of the word reasonable is 
seriously necessary in regard to this  issue). Enormous opportunities for 
efficiency and conservation, distributive  energy and clean technologies exist. 
ISSUE 6:         Will  the proposed generating units provide the most 
cost-effective source of power,  as this criterion is used in Section 403.519(4), 
Florida Statutes?  
Position: No, this project’s  costs must be compared with an equal amount of 
analysis to a renewable/  efficiency option. The proposed nuclear project time 
line extends over a period  that would allow the monies dedicated to the 
project to incrementally provide  for FPL customer energy needs by the use of 
efficiency programs, elevated  standards of power usage and investments in clean 
energy technologies, without  the costly, problematic issues of long term toxic 
waste management, among other  things.  
ISSUE 7:         Based on the resolution of the foregoing issues, should the 
Commission  grant Florida Power & Light Company’s petition to determine the 
need for the  proposed generating units? 
Position:  No 
ISSUE 8:         Should this docket be closed? 
Position: Yes, this docket should be closed and  FPL’s petition denied   
due to the lack of adequate  analysis of all reasonable options and the   
extreme risk and inability to  project accurate costs which in turn stifles the 
development and investment in  efficiency and new clean technologies 
Additional  Issues 
FPL 
ISSUE 9:         If  the Commission grants Florida Power & Light Company’s 
petition to determine  the need for the proposed generating units, should the 
Commission’s order  expressly state support for the development of new nuclear 
generation, affirm  the need to take steps now to preserve new nuclear 
generation as a resource  option to meet future customer needs, acknowledge the risks 
and costs associated  with a project of such magnitude and the corresponding 
stepwise role of the  annual review process and emphasize the importance of 
continued regulatory  support throughout the process? (FPL 8) 
Position: It is our position, as stated  during the effort to identify 
issues, that issues 9-12 are not appropriately  placed in this docket.  In  
particular reference to issue 9 if we are incorrect in our assessment of the  
inappropriateness of the placement of these issues in this docket we have listed  an 
additional issue for ourselves that is identified in the pending motions  
portion of this document that requests specific actions by the PSC in the event  
they deny this petition. 
ISSUE 10:       If the  Commission grants Florida Power & Light Company’s 
petition to determine the  need for the proposed generating units, is it prudent 
for FPL to make advance  payments for such long-lead procurement items as are 
reasonably necessary to  preserve the potential for 2018-2020 in-service dates 
for the proposed  generating units? (FPL 9) 
Position: No, we believe  issue 10 is not appropriate for this docket. 
ISSUE 11:       If the  Commission grants Florida Power & Light Company’s 
petition to determine the  need for the proposed generating units, are prudent 
advancepayments made prior  to the completion of the proposed generating units’ 
site clearing work properly  characterized as “pre-construction costs,” to be 
recovered pursuant to the  mechanism provided in Rule 25-6.0423, F.A.C.? (FPL 
10) 
Position: No, we believe issue 11 is not appropriate for this docket 
ISSUE 12:       If  FPL were to file for  recovery by May 1, 2008, would 
pre-construction costs associated with the  proposed generating units that the 
Commission determines are reasonable and  prudent be included for cost recovery 
purposes as a component of the 2009  Capacity Cost Recovery Factor in the 
annual Fuel and Purchased Power Cost  Recovery proceeding, pursuant to Rule 
25-6.0423(5) (c), F.A.C.? (FPL  11) 
Position: No, we believe  issue 12 is not appropriate for this docket 
FMPA/FMEA 
ISSUE 13:       Does  FPL's nuclear power plant petition contain a summary of 
any discussions with  other electric utilities regarding ownership of a 
portion of the plant by such  electric utilities, consistent with the requirements 
of Rule 25-22.081, F.A.C.?  (FMPA/FMEA 7) 
Position: No, and the fact that FPL’s  petition does not contain a summary of 
any discussions they had with other  electric utilities regarding ownership 
of the portion of the plant should be  rectified by FPL amending their original 
petition to include the required  information or, if there have been no 
preliminary discussions as claimed, and no  summary is possible, FPL should be 
required to withdraw their present petition  and submit an accurate correct one 
starting from square one. 
OUC 
ISSUE 14:       Does  not 403.519(4)(b), Fla. Stat., stating that the 
Commission shall “take into  account matters within its jurisdiction, which it deems 
relevant” allow the  Commission to conclude that co-ownership is relevant 
especially in light of  (4)(b)(2) which requires the Commission to consider 
whether the approval will  enhance the reliability of power production within the 
state (not just in FPL’s  territory) and (4)(b)(3) requiring the Commission to 
take into account the  plant’s contribution to the long-term stability and 
reliability of the electric  grid? (OUC 1)   
Position: No. 
ISSUE 15:       Did Florida  Power and Light’s Petition, as required by Rule 
25-22.081 (2) (d) F.A.C.,  contain a summary of any discussions Florida Power 
and Light had with other  electric utilities concerning the other electric 
utilities’ ownership of a  portion of the Florida Power and Light nuclear plant? 
(OUC 2) 
Position: No, and the fact that FPL’s  petition does not contain a summary of 
any discussions they had with other  electric utilities regarding ownership 
of the portion of the plant should be  rectified by FPL amending their original 
petition to include the required  information or, if there have been no 
preliminary discussions as claimed, and no  summary is possible, FPL should be 
required to withdraw their present petition  and submit an accurate correct one 
starting from square one. 
ISSUE 16:       Does  403.519(4)(a)(5), Fla. Stat., and Rule 25-22.081(2)(d) 
F.A.C., create any duty  on Florida Power & Light (“FPL”) to initiate 
discussion with other utilities  that might have an interest in ownership of a 
portion of the nuclear plants or  is this legislation and rule meaningless and may 
be ignored all together (FPL  says they can satisfy law and rule by not having 
any discussions and reporting  that fact at FPL Response, Paragraph 2, page 
2)? (OUC 4) 
Position:  No, to the  following sentence, “Does  403.519(4)(a)(5), Fla. 
Stat., and Rule 25-22.081(2)(d)  F.A.C., create any duty on Florida Power  & Light 
(“FPL”) to initiate discussion with other utilities that might have  an 
interest in ownership of a portion of the nuclear plants.” 
No  to the following portion of issue 16  “or is this legislation and rule 
meaningless and may be ignored all  together.”                                   
                                         
Yes  to the following portion of issue 16 “FPL says they can satisfy law and 
rule  by  not having any discussions and reporting that fact” (See our  
position on issue 14) 
ISSUE 17:       Does  OUC, a utility that presently has ownership in two 
nuclear power plants, have a  substantial interest in having meaningful 
discussions with Florida Power &  Light regarding ownership of a portion of the nuclear 
power plants at issue here  as required by 403.519(4)(a)(5), Fla. Stat.?? (OUC 
5) 
Position: No, no such  requirement exists 
ISSUE 18:       Should  the Commission infer any intent by Legislature from 
actions that were not taken  by the Legislature (an amendment was proposed but 
withdrawn)? (OUC 6) 
Position: No. 
Seminole 
ISSUE 19:       Has FPL  engaged in meaningful discussions with other 
electric utilities regarding  ownership of a portion of the proposed nuclear plants 
by such utilities?  (SEMINOLE 7) 
Position: Yes, FPL has stated in their  petition on page 37 IX that “FPL has 
held preliminary discussions regarding the  potential for ownership 
participation with several Florida utilities who  have expressed interest. As FPL 
proceeds through the licensing phase and begins  dedicated commercial negotiations 
with the selected vendor, opportunities for  partnership with Florida utilities 
will continue to be  explored.” The fact that FPL’s petition does not 
contain a summary of any  discussions they had with other electric utilities 
regarding ownership of the  portion of the plant should be rectified by FPL amending 
their original petition  to include the required information or, if there have 
been no preliminary  discussions as claimed, and no summary is possible, FPL 
should be required to  withdraw their present petition and submit an accurate 
correct one starting from  square one. 
ISSUE 20:       If not,  should the Commission require such discussions?  
(SEMINOLE 8) 
Position:  No, only a summary is provided by  law.   
5.  Stipulated issues 
None at this time. 
    1.  Pending motions and other matters upon  which action is sought
If the commission denies  FPL’s petition for the determination of need for 
the proposed units, should the  commission order expressly state support for a 
comprehensive analysis of all  energy efficiency and conservation 
opportunities, all clean renewable generating  options and the value of an expanded net 
metering/ distributive energy program  and research into the application of 
innovative methods of reordering the  competitive marketplace in Florida to more 
effectively and prudently address the  energy needs of the State’s residents 
financed with the billions of that would  have been used to pay for the nuclear 
power plants? 
7. Pending claim for  confidentiality 
None  at this time 
8. Objections to witness  qualifications as an expert, none. 
None at this time 
9. Compliance with Order  No, PSC-07-0869-PCO-El, 
At this time persons who are intervenors  are unaware of any requirements of 
the    Order Establishing  procedure with which they can not comply. 
Respectfully submitted this 4th day of January, 2008. 
s/ Bob Krasowski 
s/  Jan Krasowski 
Bob and Jan Krasowski 
1086 Michigan  Ave. 
Naples,  FL.34103-3857 
239-434-0786



**************Start the year off right.  Easy ways to stay in shape.     
http://body.aol.com/fitness/winter-exercise?NCID=aolcmp00300000002489
-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://mail.energyjustice.net/pipermail/nukenet_energyjustice.net/attachments/20080107/04dce17c/attachment-0001.html 


More information about the Nukenet mailing list