[NukeNet] Individual Action in progress, Florida Alliance update, Part 2b of 2A&B.
Minimushomines at aol.com
Minimushomines at aol.com
Mon Jan 7 20:12:23 EST 2008
Additional Issues
FPL
ISSUE 9: If the Commission grants Florida Power & Light Company’s
petition to determine the need for the proposed generating units, should the
Commission’s order expressly state support for the development of new nuclear
generation, affirm the need to take steps now to preserve new nuclear
generation as a resource option to meet future customer needs, acknowledge the risks
and costs associated with a project of such magnitude and the corresponding
stepwise role of the annual review process and emphasize the importance of
continued regulatory support throughout the process? (FPL 8)
Position: It is our position, as stated during the effort to identify
issues, that issues 9-12 are not appropriately placed in this docket. In
particular reference to issue 9 if we are incorrect in our assessment of the
inappropriateness of the placement of these issues in this docket we have listed an
additional issue for ourselves that is identified in the pending motions
portion of this document that requests specific actions by the PSC in the event
they deny this petition.
ISSUE 10: If the Commission grants Florida Power & Light Company’s
petition to determine the need for the proposed generating units, is it prudent
for FPL to make advance payments for such long-lead procurement items as are
reasonably necessary to preserve the potential for 2018-2020 in-service dates
for the proposed generating units? (FPL 9)
Position: No, we believe issue 10 is not appropriate for this docket.
ISSUE 11: If the Commission grants Florida Power & Light Company’s
petition to determine the need for the proposed generating units, are prudent
advancepayments made prior to the completion of the proposed generating units’
site clearing work properly characterized as “pre-construction costs,” to be
recovered pursuant to the mechanism provided in Rule 25-6.0423, F.A.C.? (FPL
10)
Position: No, we believe issue 11 is not appropriate for this docket
ISSUE 12: If FPL were to file for recovery by May 1, 2008, would
pre-construction costs associated with the proposed generating units that the
Commission determines are reasonable and prudent be included for cost recovery
purposes as a component of the 2009 Capacity Cost Recovery Factor in the
annual Fuel and Purchased Power Cost Recovery proceeding, pursuant to Rule
25-6.0423(5) (c), F.A.C.? (FPL 11)
Position: No, we believe issue 12 is not appropriate for this docket
FMPA/FMEA
ISSUE 13: Does FPL's nuclear power plant petition contain a summary of
any discussions with other electric utilities regarding ownership of a
portion of the plant by such electric utilities, consistent with the requirements
of Rule 25-22.081, F.A.C.? (FMPA/FMEA 7)
Position: No, and the fact that FPL’s petition does not contain a summary of
any discussions they had with other electric utilities regarding ownership
of the portion of the plant should be rectified by FPL amending their original
petition to include the required information or, if there have been no
preliminary discussions as claimed, and no summary is possible, FPL should be
required to withdraw their present petition and submit an accurate correct one
starting from square one.
OUC
ISSUE 14: Does not 403.519(4)(b), Fla. Stat., stating that the
Commission shall “take into account matters within its jurisdiction, which it deems
relevant” allow the Commission to conclude that co-ownership is relevant
especially in light of (4)(b)(2) which requires the Commission to consider
whether the approval will enhance the reliability of power production within the
state (not just in FPL’s territory) and (4)(b)(3) requiring the Commission to
take into account the plant’s contribution to the long-term stability and
reliability of the electric grid? (OUC 1)
Position: No.
ISSUE 15: Did Florida Power and Light’s Petition, as required by Rule
25-22.081 (2) (d) F.A.C., contain a summary of any discussions Florida Power
and Light had with other electric utilities concerning the other electric
utilities’ ownership of a portion of the Florida Power and Light nuclear plant?
(OUC 2)
Position: No, and the fact that FPL’s petition does not contain a summary of
any discussions they had with other electric utilities regarding ownership
of the portion of the plant should be rectified by FPL amending their original
petition to include the required information or, if there have been no
preliminary discussions as claimed, and no summary is possible, FPL should be
required to withdraw their present petition and submit an accurate correct one
starting from square one.
ISSUE 16: Does 403.519(4)(a)(5), Fla. Stat., and Rule 25-22.081(2)(d)
F.A.C., create any duty on Florida Power & Light (“FPL”) to initiate
discussion with other utilities that might have an interest in ownership of a
portion of the nuclear plants or is this legislation and rule meaningless and may
be ignored all together (FPL says they can satisfy law and rule by not having
any discussions and reporting that fact at FPL Response, Paragraph 2, page
2)? (OUC 4)
Position: No, to the following sentence, “Does 403.519(4)(a)(5), Fla.
Stat., and Rule 25-22.081(2)(d) F.A.C., create any duty on Florida Power & Light
(“FPL”) to initiate discussion with other utilities that might have an
interest in ownership of a portion of the nuclear plants.”
No to the following portion of issue 16 “or is this legislation and rule
meaningless and may be ignored all together.”
Yes to the following portion of issue 16 “FPL says they can satisfy law and
rule by not having any discussions and reporting that fact” (See our
position on issue 14)
ISSUE 17: Does OUC, a utility that presently has ownership in two
nuclear power plants, have a substantial interest in having meaningful
discussions with Florida Power & Light regarding ownership of a portion of the nuclear
power plants at issue here as required by 403.519(4)(a)(5), Fla. Stat.?? (OUC
5)
Position: No, no such requirement exists
ISSUE 18: Should the Commission infer any intent by Legislature from
actions that were not taken by the Legislature (an amendment was proposed but
withdrawn)? (OUC 6)
Position: No.
Seminole
ISSUE 19: Has FPL engaged in meaningful discussions with other
electric utilities regarding ownership of a portion of the proposed nuclear plants
by such utilities? (SEMINOLE 7)
Position: Yes, FPL has stated in their petition on page 37 IX that “FPL has
held preliminary discussions regarding the potential for ownership
participation with several Florida utilities who have expressed interest. As FPL
proceeds through the licensing phase and begins dedicated commercial negotiations
with the selected vendor, opportunities for partnership with Florida utilities
will continue to be explored.” The fact that FPL’s petition does not
contain a summary of any discussions they had with other electric utilities
regarding ownership of the portion of the plant should be rectified by FPL amending
their original petition to include the required information or, if there have
been no preliminary discussions as claimed, and no summary is possible, FPL
should be required to withdraw their present petition and submit an accurate
correct one starting from square one.
ISSUE 20: If not, should the Commission require such discussions?
(SEMINOLE 8)
Position: No, only a summary is provided by law.
5. Stipulated issues
None at this time.
1. Pending motions and other matters upon which action is sought
If the commission denies FPL’s petition for the determination of need for
the proposed units, should the commission order expressly state support for a
comprehensive analysis of all energy efficiency and conservation
opportunities, all clean renewable generating options and the value of an expanded net
metering/ distributive energy program and research into the application of
innovative methods of reordering the competitive marketplace in Florida to more
effectively and prudently address the energy needs of the State’s residents
financed with the billions of that would have been used to pay for the nuclear
power plants?
7. Pending claim for confidentiality
None at this time
8. Objections to witness qualifications as an expert, none.
None at this time
9. Compliance with Order No, PSC-07-0869-PCO-El,
At this time persons who are intervenors are unaware of any requirements of
the Order Establishing procedure with which they can not comply.
Respectfully submitted this 4th day of January, 2008.
s/ Bob Krasowski
s/ Jan Krasowski
Bob and Jan Krasowski
1086 Michigan Ave.
Naples, FL.34103-3857
239-434-0786
**************Start the year off right. Easy ways to stay in shape.
http://body.aol.com/fitness/winter-exercise?NCID=aolcmp00300000002489
-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://mail.energyjustice.net/pipermail/nukenet_energyjustice.net/attachments/20080107/1c4b5792/attachment-0001.html
More information about the Nukenet
mailing list